# South Korea’s AI Chip Hub Faces Power and Water Backlash in Southwest

> Source: <https://insideai.news/news/ai-hardware-infrastructure/south-koreas-ai-chip-hub-faces-power-and-water-backlash-in-southwest/4762/>
> Published: 2026-07-21 03:18:17+00:00

**July 21, 2026, (Inside AI) —** South Korea’s ambition to build a massive semiconductor hub in its southwest by **2030** is colliding with local opposition over the project’s enormous power and water demands. The Honam industrial complex, estimated at **800 trillion won ($540 billion)**, is central to President Lee Jae Myung’s plan to decentralize the AI chip boom beyond Seoul. But residents in **Gwangju**, **North Jeolla**, and **South Jeolla** are pushing back against new transmission lines, nuclear reactors, and dam expansions.

The four planned chip fabrication plants could consume **70% to 80%** of the region’s current annual electricity, according to analysts. **Neal Won**, principal analyst at **S&P Global Energy**, told Reuters the surge is unprecedented.

“A huge amount of new power demand is coming into a region that previously had little, and that's the core of the problem,” Won said.

This tension echoes delays at chip clusters in **Yongin**, near Seoul, where **Samsung Electronics** and **SK Hynix** have faced water and power bottlenecks. **Mayor Lee Sang-il** said SK Hynix’s first fabs, announced in **2019**, were delayed months due to resident opposition to a water supply weir.

“The responsibility to calm opposing voices and resolve differences lies with the central government,” Lee said.

South Korea’s energy ministry argues the southwest already generates more power than it uses, reducing the need for long-distance transmission. It plans to work with local governments and consider underground lines. **Energy Minister Kim Sung-whan** has also floated building new nuclear reactors and small modular reactors.

But in **Yeonggwang** county, **Roh Byeong-nam**, a farmer and co-chair of a local anti-nuclear coalition, vowed legal challenges to any nuclear expansion.

“To now talk about new construction, on top of extending the lifespan of ageing reactors, is nothing less than a declaration that Yeonggwang will become a nuclear testing ground and eventually a permanent nuclear waste site,” Roh said.

Water supply is equally contentious. The cluster needs about **650,000 metric tons** of water daily—more than Gwangju’s entire residential supply. Developers aim to raise **Dongbok Dam** to secure an additional **250,000 metric tons** a day, but residents say they were not consulted.

“This is the same as dam construction,” said **Kim Kwang-jin**, head of a dam-residents group, estimating **1,500 to 1,600** affected households. “They announced it unilaterally without considering resident acceptance.”

## Infrastructure Demands Outpace Public Consent

The Honam complex’s power needs highlight a broader challenge: South Korea’s semiconductor expansion is outpacing its energy and water infrastructure. The country is the world’s largest memory chip maker, but past projects show that securing resources is often the biggest hurdle. In **2022**, Samsung delayed a **$17 billion** Texas fab due to similar issues, underscoring a global pattern.

Analysts note that South Korea’s power grid is already strained. The southwest has surplus generation, but transmitting it to new fabs requires upgrades that locals oppose. The energy ministry’s plan to keep power local may reduce long-distance lines, but it doesn’t eliminate the need for new substations and reactors. Small modular reactors, while promising, are unproven at scale and face public skepticism after the **Fukushima** disaster.

Water scarcity adds another layer. Chip manufacturing is water-intensive, and the southwest is prone to droughts. The environment ministry’s plan to use reclaimed water and raise Dongbok Dam could face legal challenges. **Kim Kwang-jin**’s group argues the dam expansion would flood farmland and displace communities, echoing controversies over the **Four Major Rivers Project** in the **2010s**.

The government insists it will minimize environmental damage and continue talks, but time is short. With President Lee’s term ending in **2030**, any delays could derail the project. The central government’s role in mediating disputes is critical, as Mayor Lee Sang-il noted, but its track record is mixed. The Yongin delays show that even Seoul’s political weight can’t fast-track consent.

## A Microcosm of Global Chip Ambitions

South Korea’s struggle mirrors global tensions as nations race to onshore chip production. The **U.S. CHIPS Act**, **EU Chips Act**, and **Japan’s** subsidies all face similar infrastructure and environmental hurdles. In **Arizona**, **TSMC** faced water supply concerns; in **Germany**, **Intel’s** Magdeburg fab sparked protests over energy use. The Honam complex, if built, would be one of the largest chip hubs outside Seoul, but its success hinges on resolving the resource paradox.

The energy ministry said the dam-raising option would minimise environmental damage and relocation compared with constructing a new dam, and it will continue talks with **Gwangju** and local residents to prevent opposition or infrastructure issues from delaying the project. Yet, as **Roh Byeong-nam**’s litigation threat shows, legal battles could stall progress for years. The outcome will test whether South Korea can balance industrial ambition with democratic consent, a dilemma that will define the next decade of AI hardware expansion.