# OU Study: 212 Data Centers, 11 Firms, 1 Top Factor

> Source: <https://shattered.io/ou-study-212-data-centers-11-companies-land-use-diversity-nov-25/>
> Published: 2026-11-25 03:00:50+00:00

**Key takeaway:** Across 212 U.S. data centers run by 11 major technology companies, land-use diversity — a mix of housing, commerce, industry and services — tracked more strongly with siting than electrical substations, major roads or IT worker concentrations.

A new study from the University of Oklahoma puts hard numbers behind a question that planning boards across the country keep asking: what draws [data centers](https://shattered.io/equinix-quantum-computing-data-center-four-production-requirements-six-site-checks/) to a community? According to [the University of Oklahoma announcement](https://www.ou.edu/news/articles/2026/november/what-draws-data-centers-to-a-community), researchers examined 212 U.S. data centers run by 11 major technology companies, including Amazon, Microsoft, Google and Meta. Land-use diversity came out as the strongest factor, ahead of the other signals the team tested.

The story is dated November 20, 2026, with an update on November 22. It lands at a moment when cloud and AI operators are hunting for sites faster than most local governments can write zoning rules. Our earlier look at [an immersion-only data center pitched at under 30,000 square feet](https://shattered.io/it-availability-immersion-only-data-center-under-30000-sq-ft/) showed how much the building itself is changing. The OU work asks a different question: not how to build the hall, but why a given town gets it.

This analysis walks through what the study found, what it left out, and what the findings mean for cloud planners, local officials and anyone who has watched a substation upgrade or a rezoning notice appear at the edge of town. We keep to the facts the university has published. Where the record is thin, we say so.

Don't miss new tech stories on Google

Add Shattered once in the Google app and our stories show up in your news suggestions.

[Add now](https://www.google.com/preferences/source?hl=en&q=https%3A%2F%2Fshattered.io%2F)

## What the OU Study Actually Measured

Kijin Seong, Ph.D., is an assistant professor in the Division of Planning, Landscape Architecture and Design at OU’s Christopher C. Gibbs College of Architecture. He co-authored the research. The team did not survey executives or ask companies to explain their reasoning. Instead, it looked at where 212 existing facilities sit and tested which local characteristics tracked with those locations.

The sample spans 11 major technology companies. Amazon, Microsoft, Google and Meta are named in the announcement, and the other seven are not identified in the material we reviewed. That matters for readers who want company-by-company patterns. The published summary reports aggregate findings, so we cannot say whether Meta favors different communities than Microsoft does.

The analysis grouped its explanatory factors into three families: land use, infrastructure and workforce. Land use covers the mix of activities in the surrounding area. Infrastructure covers electrical substations and major roads. Workforce covers concentrations of information technology workers. Those three families gave the researchers a way to compare very different sites on the same terms.

| Item | What the OU announcement reports | 
|---|---|
| Sites examined | 212 U.S. data centers | 
| Operators covered | 11 major technology companies | 
| Named companies | Amazon, Microsoft, Google, Meta | 
| Strongest factor | Land-use diversity | 
| Other factors that helped explain siting | Electrical substations, major roads, IT worker concentrations | 
| Lead researcher profile | Kijin Seong, Ph.D., assistant professor, OU Gibbs College of Architecture | 
| Story date | November 20, 2026 (updated November 22, 2026) | 

## Land-Use Diversity: The Strongest Factor in Data Center Site Selection

The headline result is the one that surprises people. Land-use diversity, meaning a neighborhood or district that mixes housing, commerce, industry and services, was the strongest factor the analysis identified. Many readers would have guessed that wide-open, single-purpose land wins. The OU team found the reverse pattern holds up better in the data.

Why would a mixed area attract a server hall? The study summary does not offer a causal story, and we will not invent one. What we can say is that mixed-use areas tend to come with the things a large facility needs to function: established utility service, road networks, nearby workers and a local government used to permitting different kinds of buildings. A diverse land-use pattern may work as a proxy for all of that.

### What diversity does and does not mean

Diversity here describes the surrounding community, not the data center parcel. A site can sit on a quiet lot and still score high if the district around it mixes uses. For local officials, that distinction changes the pitch. A town does not need to rezone everything for servers. It needs to look like a place where varied development already happens.

Practitioners have long published checklists that treat land as a gate. A [site selection criteria guide from Base Operations](https://www.baseoperations.com/article/data-center-site-selection-criteria) is one example of that genre, which lists the factors developers screen before they commit. The OU analysis adds something those checklists rarely supply: a pattern drawn from where 212 real facilities actually went.

## Substations, Roads and IT Workers: The Supporting Signals

Three more factors helped explain where facilities landed. Proximity to electrical substations, access to major roads and concentrations of information technology workers all showed up in the analysis. None of them beat land-use diversity, but each one added explanatory power.

The substation finding fits the physical logic of the business. A data hall is, at its core, a very large electrical load with cooling attached. Sitting close to a substation shortens the path between the grid and the racks. It does not guarantee capacity, and the OU summary reports no megawatt figures, so readers should not read the finding as a statement about how much power any site gets.

Major roads matter for less glamorous reasons. Construction crews, generators, cooling equipment and replacement hardware all arrive by truck. Roads also bring staff to the door during shifts. The study treats road access as one measurable proxy for that logistics burden.

The IT workforce signal is the most interesting for smaller communities. Facilities cluster where technology workers already live. That suggests that talent, not just land and power, shapes the map. Towns hoping to land a cloud region should ask whether they can supply or attract the people who run it.

## What Site Selectors Say About Power and Workforce

The OU findings line up with how industry practitioners describe the job. Seong himself framed the basics plainly in a report from [okcfox.com](https://okcfox.com/news/local/ou-researcher-focuses-on-factors-drawing-data-centers-to-communities). He said, “The buildings that hold data centers need land, a lot of electricity, water for cooling and fiber connections.”

Note that water and fiber appear in that quote, yet the announcement lists land use, infrastructure (substations and roads) and workforce as the factors the analysis found helpful. We have no confirmed water-use figure or fiber measurement from the study, so we treat those as background requirements Seong described rather than tested results.

Industry voices stress power even more bluntly. Chris Lloyd, senior vice president and director of infrastructure and economic development at McGuireWoods Consulting, put it in three words in [a site selector discussion published by SEDC](https://www.sedc.org/news/site-selector-perspectives-on-data-centers): “Power is king.” That view sits comfortably beside the OU substation result.

On staffing, Courtland Robinson, a director at Brasfield and Gorrie, told the same SEDC discussion that “For a rural community, the workforce is a big consideration.” He also described a workaround developers use when local talent is thin: “You can import a certain amount of labor to a new facility where a workforce for those data center occupations didn’t exist.”

That second remark complicates the OU workforce finding in a useful way. If operators can bring in staff, then a missing IT workforce may not block a project outright. It may simply raise the cost and slow the ramp. Seong’s own framing points to what the study is for. In OU’s words, “Our study serves as a starting point for communities preparing for the physical demands of the AI boom.”

## How the Findings Compare With Standard Site-Selection Frameworks

Data center site selection already has a deep literature, much of it written by consultants, engineering firms and state extension programs. The OU work differs in method. It starts from observed locations and works backward, while most checklists start from what a developer wants and work forward. Both approaches have a job to do.

Engineering firms such as WSP publish guidance on [data center site selection for long-term resilience](https://www.wsp.com/en-nz/insights/data-center-site-selection-long-term-resilience), which frames siting as a question of how a facility holds up over decades. Insurance and risk advisers such as Gallagher have written about the risk dimensions that go beyond power and land. Academic and extension groups, including a Blueprint Kentucky publication from the University of Kentucky, aim their material at the communities on the receiving end.

| Approach | Starting point | Main strength | Main limit | 
|---|---|---|---|
| OU spatial study | Locations of 212 existing facilities | Shows what real sites have in common | Aggregate result, no company-level detail published | 
| Consultant checklists (for example Base Operations) | Developer screening criteria | Practical, ordered list of gates | Not tied to a measured sample in the same way | 
| Engineering resilience guidance (for example WSP) | Long-term performance of a site | Looks at durability over a facility’s life | Written for owners, not for host towns | 
| Risk and insurance commentary (for example Gallagher) | Exposure beyond power and land | Flags hazards checklists skip | Qualitative by nature | 
| University extension guides (for example Blueprint Kentucky) | Needs of the host community | Speaks to local officials directly | State-specific framing | 

Read together, the sources agree on the broad shape of the problem. Power, land and people come first. They disagree about emphasis, and the OU data adds weight to the idea that the character of the surrounding community counts for more than a raw land listing suggests.

## What the Study Does Not Say

Good reporting on a study includes its silences. The material we reviewed does not provide a specific investment amount, a job count, a tax incentive, a water-use figure, an electricity requirement or a construction date. It also carries no quoted statement from a company or a community official. Anyone who cites those details alongside the OU study is adding them from elsewhere.

The announcement also does not name the other two researchers, so we leave their identities out. And it describes factors that helped explain locations. That wording describes association. It does not prove that a substation or a diverse neighborhood caused a company to pick a town.

| Claim readers may see | Status in the OU announcement | 
|---|---|
| 212 facilities, 11 companies studied | Confirmed | 
| Land-use diversity is the strongest factor | Confirmed | 
| Substations, major roads and IT workers help explain siting | Confirmed | 
| Specific investment dollars per site | Not provided | 
| Jobs created per facility | Not provided | 
| Tax incentives granted | Not provided | 
| Water or electricity demand figures | Not provided | 
| Quotes from company or town officials | Not provided | 

## Why Land-Use Diversity Matters for Cloud Infrastructure Planning

For cloud teams, siting is a supply chain problem. Every new region or availability zone depends on a parcel, a grid connection and a staffing plan. If the OU result holds up, planners should score candidate towns on the mix of activity around the parcel as well as on the parcel itself.

That has a practical edge. A diverse area usually has more existing permits, more utility relationships and more neighbors who already live next to commercial buildings. Those traits can shorten the path from announcement to ribbon-cutting. They can also draw sharper scrutiny, because a mixed area has more residents close enough to object.

Our cloud coverage keeps returning to the same tension. Operators want speed, and communities want a say. Readers following the wider cloud infrastructure beat can find more in our [cloud computing section](https://shattered.io/cloud-computing/), where siting, capacity and cost stories sit side by side.

## The Grid Question Behind the Substation Finding

Proximity to a substation helped explain where the 212 facilities went, and that points at the grid as the real gatekeeper. A town can have land, roads and workers and still stall if the local utility cannot deliver power on the developer’s schedule.

Operators are responding with engineering as well as site choice. Our piece on [7 technologies that keep data centers on without grid overloads](https://shattered.io/7-technologies-keep-data-centers-on-without-grid-overloads/) covers the tools that reduce the strain a facility puts on its neighbors. Those tools may change the siting math over time, since a site that can soften its own load may not need to sit as close to a strong substation.

The cost side is moving too. Our report on [reported 45% price hikes by AI server makers](https://shattered.io/ai-server-makers-reported-45-percent-price-hikes-signed-contracts-ram-shortage/) shows that hardware inside the hall is getting more expensive just as the buildings around it get harder to place. When both sides tighten, a siting edge becomes worth real money.

## Workforce and the Rural Tradeoff

The IT workforce result carries a tension for rural and small-town leaders. If facilities cluster where technology workers already live, then places without that talent pool start behind. Robinson’s comment about importing labor suggests developers can bridge part of that gap, but it comes at a price.

Local officials can respond in two ways. They can invest in training so the workforce shows up before the project does, or they can accept that early staff will arrive from elsewhere and plan housing and services accordingly. Neither path is free, and the OU summary does not rank them.

Other countries are wrestling with the same question. Our coverage of [South Africa’s R100M AI venture fund plan](https://shattered.io/south-africa-r100m-ai-venture-fund-70-percent-african-data-centers-90-day-plan/) shows a government tying capital to local data center capacity, which is one way to build the talent base first.

## Security, Oversight and the Community Risk Picture

A facility that draws power, workers and fiber also draws attention. Security officials have started to treat large server sites as assets worth protecting. In our report on [the ASIO chief’s warning about 2 data center access risks](https://shattered.io/asio-burgess-data-centre-ai-warning-physical-virtual-access-foreign-interference/), the concern centered on both physical and virtual access to these buildings.

The OU study does not address security, and we do not claim it does. Still, the siting pattern has security implications. Facilities concentrated in diverse, well-connected districts sit near homes, businesses and roads. Planners in those districts should expect questions about emergency response, perimeter control and who has access to what.

Public guidance is starting to catch up. A Blueprint Kentucky publication on data center development considerations speaks directly to host communities, and risk advisers have argued that site choice involves exposures well beyond power and land. The OU result gives those conversations a data point on where the buildings actually go.

## Market Impact: Who Gains From a Clearer Siting Map

A study like this shifts bargaining power in small ways. When a community can point to published evidence about what operators look for, it can prepare before a developer shows up. When developers can point to the same evidence, they can target towns that already fit the profile and skip the ones that do not.

The financial backdrop raises the stakes. AI labs and cloud providers are spending heavily on compute, and our piece on [how Anthropic’s $93.5B IPO shifts the way AI compute gets funded](https://shattered.io/anthropic-93-5-billion-ipo-compute-financing-how-ai-labs-pay/) describes how capital markets are now part of the buildout. More money chasing sites means more pressure on the same short list of well-served towns.

Winners from the OU framing include mid-sized towns with mixed land use and decent grid access, which may look overlooked today. Losers could include remote areas that rely only on cheap acreage. Cheap land still helps, but the study suggests it does not carry a pitch on its own.

Oklahoma communities have a particular reason to care. The OU announcement frames the work as a starting point for places preparing for the physical demands of the AI boom. We have no confirmed project list or dollar figure for Oklahoma, so we leave that detail alone.

## Historical Context: How Siting Logic Has Shifted

For years, the popular picture of a data center site was simple: cheap land, cheap power, few neighbors. That picture still describes some projects. The OU analysis suggests it misses what most of the 212 sampled facilities have in common, since a diverse surrounding land-use mix turned out to be the strongest factor.

The shift reflects how the industry has grown. Early server rooms lived inside office buildings. Later facilities moved into purpose-built halls, and the current generation serves cloud and AI workloads at a scale that strains local infrastructure. As the buildings grew, the need for utilities, roads and staff grew with them.

Other regions show the same pressure in different forms. Our report on [Australia’s $115B AI data centre bet meeting a Trump tax threat](https://shattered.io/australia-ai-national-security-115-billion-data-centres-trump-tax-threat/) shows how siting and national policy now overlap. Siting is no longer only a real estate choice.

## Predictions: What Comes Next

These are our own forecasts, not findings from the OU study or claims from any company.

- **Planning departments will borrow the framework.** Expect local planners to start scoring their own districts on land-use mix, substation distance, road access and IT workforce, because those four measures are easy to calculate from public data.
- **Land-use diversity will enter incentive pitches.** Economic development offices that once sold acreage will start selling the character of the surrounding district.
- **Follow-up research will name more companies.** The current summary reports aggregates. Researchers and journalists will push for company-level and region-level patterns once the full methods are scrutinized.
- **Grid timing will matter more than site proximity.** As on-site load management improves, the question will shift from how close a site sits to a substation to how fast the utility can deliver capacity.
- **Community pushback will track the mixed-use pattern.** If operators keep choosing diverse districts, more residents will live near new facilities, and hearings will grow more crowded.

## What Communities and Cloud Teams Should Do Now

The study offers a short list of practical moves for both sides of the table. None of them rely on figures the announcement does not supply.

| Audience | Action | Study factor it connects to | 
|---|---|---|
| Local planners | Map land-use mix across candidate districts | Land-use diversity | 
| Utilities and town officials | Inventory substations and spare capacity | Electrical substations | 
| Transportation staff | Check truck access to major roads | Major roads | 
| Economic development teams | Document the local IT talent pool and training options | IT worker concentrations | 
| Cloud site teams | Score the surrounding district, not just the parcel | Land-use diversity | 
| Residents | Ask for public data on power, water and traffic before approvals | All of the above | 

The takeaway: the OU team gave communities a map of what operators have already favored. It did not hand out a guarantee. Towns that fit the profile should prepare, and towns that do not should decide whether they want to.

## FAQ: What Draws Data Centers to a Community

### What draws data centers to a community, according to the OU study?

The analysis found that land use, infrastructure and workforce characteristics helped explain where companies built facilities. Land-use diversity was the strongest factor. Proximity to electrical substations, access to major roads and concentrations of information technology workers also helped.

### How many data centers did the researchers examine?

The study examined 212 U.S. data centers operated by 11 major technology companies, including Amazon, Microsoft, Google and Meta.

### Who led the research?

Kijin Seong, Ph.D., an assistant professor in the Division of Planning, Landscape Architecture and Design at the University of Oklahoma’s Christopher C. Gibbs College of Architecture, co-authored it. The announcement material we reviewed does not name the other two researchers.

### Does the study say how much power or water a data center uses?

No. The material we reviewed provides no electricity requirement, water-use figure, investment amount, job count or tax incentive. Seong did describe water and fiber as basic needs in a media interview, but those are not reported as tested factors.

### Does land-use diversity mean data centers prefer busy city centers?

Not necessarily. The finding describes the mix of land uses around a site. A facility can sit on a quiet parcel inside a district that mixes housing, commerce and industry. The summary does not say sites prefer downtown areas.

### Does the study prove that substations or workers cause a company to choose a site?

No. The factors helped explain where facilities were built, which describes an association. The announcement does not claim that any one factor caused a siting decision.

### Can a town without many IT workers still attract a data center?

Possibly. Courtland Robinson of Brasfield and Gorrie said in the SEDC discussion that developers can import a certain amount of labor when a local workforce does not exist. The OU study found IT worker concentrations helped explain siting, so a thin local talent pool may raise costs even if it does not rule a town out.

### When was the OU announcement published?

The story is dated November 20, 2026, with an update on November 22, 2026.