- Ontario opened a 30-day consultation on its Data Centre Playbook beginning August 13, 2026. [1] - The framework proposes a separate electricity rate class for new data centres above 1MW and measures to encourage operators to build dedicated generation. [1] - Projects would be assessed against three pillars: Ontario economic development, data security and digital sovereignty, and community investment and public confidence. [1] - The province says data centres should pay for their impact on the electricity system so costs are not passed on to residential customers. [1] - Ontario’s data centre demand forecast represents about 13% of new provincial electricity demand by 2035.
[2] Ontario Premier Doug Ford’s government launched a Data Centre Playbook on August 13, 2026, proposing a framework for attracting and evaluating data centre investment while addressing the sector’s effect on electricity infrastructure and host communities. The announcement was made in Guelph, Ontario, and opened a 30-day public comment period through provincial registries. [1]
The framework is not, by itself, a binding operating standard. It sets out strategic priorities for assessing projects and builds on legislation that gives the province authority to approve or reject certain large-load electricity connections. Ontario said the policy is intended to support investment, preserve Canadian data residency and ensure communities receive benefits from new facilities. [1][2]
The Framework #
Ontario’s proposed assessment framework has three priority pillars: economic development in Ontario; data security and digital sovereignty; and investment in host communities and public confidence. [1]
The framework identifies potential local benefits including apprenticeship and reskilling opportunities, community amenities, critical infrastructure improvements, job creation and increased demand for local accommodation. It calls for data centre investments to contribute “significantly” to host communities, but does not set a single province-wide dollar threshold for those contributions. [1]
Power and Rate Design #
The playbook proposes that new data centres pay the cost of their impact on Ontario’s electricity system. Measures under consideration include encouraging projects to build their own generation and creating a separate electricity rate class for new data centres above 1MW. [1]
The policy follows Ontario’s 2025 electricity legislation and consultation process, which created authority for the province to evaluate and approve certain data centre connection requests before utilities connect them to the grid. The earlier proposal identified economic development, domestic data hosting and system capacity as factors in the connection process. [2]
Investment Case and Consultation #
Ontario said it will rely on non-financial support rather than direct financial incentives to attract data centre investment. The province is positioning its electricity system, available land, cooler climate and skilled workforce as the core elements of that offer. [1]
The government links the playbook to a broader provincial AI strategy that it says could generate $122 billion in economic growth by 2035 and more than 17,000 new jobs annually. Those figures are government projections, not commitments attached to individual data centre projects. [1]
Ontario’s 2026 budget said the province has approximately 100 data centres and is prioritizing electricity access for facilities that create high-quality jobs, support domestic data hosting and strengthen the digital economy. [3]
What Happens Next #
The public comment period for the new playbook began August 13, 2026, through the Environmental Registry of Ontario and Ontario Regulatory Registry. The province has not announced a final implementation date for the proposed rate class or other measures described in the framework. [1]
Ontario’s earlier electricity consultation recorded concerns about grid capacity, generation requirements and the need for a clear connection process. The province said it was reviewing those comments while developing a regulatory framework for large data centre growth. [2]