AI data centers turn to industrial boilers and steam turbines as gas turbine backlogs grow

Babcock & Wilcox signed a $2.4 billion design-build agreement to deliver 1.2 GW of natural gas-fired boiler-steam capacity for Applied Digital's AI campuses, as multi-year backlogs for large-frame gas turbines push data center operators toward industrial boilers paired with steam turbines. Siemens Energy agreed to supply 20 steam turbine-generator sets rated at 50 MW each, totaling 1 GW, under an arrangement with an August 2026 notice-to-proceed timeline, while B&W's 1 GW initiative for Applied Digital targets operation by 2028 with a March 2026 notice to proceed. Applied Digital's Ellendale, North Dakota site had reached 50 MW of online capacity by late 2025, and industry projections suggest AI-scale facilities could demand tens of gigawatts of new capacity by 2030.

read2 min views2 publishedSep 10, 2026
AI data centers turn to industrial boilers and steam turbines as gas turbine backlogs grow
Image: Cryptobriefing (auto-discovered)

Babcock & Wilcox lands a $2.4 billion deal to build boiler-steam plants for Applied Digital as AI power demand outpaces conventional supply chains.

Gas turbines, the traditional workhorses for new power generation, now carry multi-year backlogs. Data center operators are turning to industrial boilers paired with steam turbines as an alternative. Babcock & Wilcox, a 157-year-old company, has signed a $2.4 billion design-build agreement to deliver 1.2 GW of natural gas-fired boiler-steam capacity for Applied Digital’s AI campuses. B&W says it can deliver packaged boiler units in about one year, a fraction of the wait time for large-frame gas turbines.

Why boilers are suddenly cool again #

AI-scale data centers are placing orders for hundreds of megawatts to gigawatt-scale gas turbines, and those orders now represent around 20% of some manufacturers’ entire gas power backlog. Natural gas-fired boilers coupled with steam turbines offer a workaround. B&W claims these packaged systems can match the peak-hour efficiency of some gas turbines.

Siemens Energy agreed to supply 20 steam turbine-generator sets, each rated at 50 MW, totaling 1 GW of capacity as part of its arrangement with B&W. That agreement carries an August 2026 notice-to-proceed timeline.

Applied Digital’s North Dakota bet #

Applied Digital’s site in Ellendale, North Dakota, had already achieved 50 MW of online capacity by late 2025. B&W’s 1 GW capacity initiative for Applied Digital is focused on natural gas-fired plants expected to be operational by 2028, with a notice to proceed in March 2026.

Industry projections suggest AI-scale facilities could demand tens of gigawatts of new capacity by 2030. A single gigawatt is roughly the output of a large nuclear plant.

Energy markets feel the pull #

Natural gas is emerging as the default fuel for AI infrastructure because it offers dispatchable, round-the-clock power that can be sited near the data center itself. As hyperscalers and AI labs secure their own on-site generation, they are effectively bypassing the utility grid for baseload power, taking on the operational complexity of running their own power plants.

Disclosure: This article was edited by Editorial Team. For more information on how we create and review content, see our

Editorial Policy.

── more in #ai-infrastructure 4 stories · sorted by recency
── more on @babcock & wilcox 3 stories trending now
sponsored brought to you by zahid.host 4,200+ EU-deployed projects
reading about agents? ship yours in a single git push.

Run your AI side-project on zahid.host

EU-based hosting, git-push deploys, automatic HTTPS, no cold starts. Free tier with a custom domain — perfect for shipping the agent you just read about.

$git push zahid main
Live at https://your-agent.zahid.host
Get free account → Pricing
from €0/mo · no card required
LIVE [news/ai-data-centers-turn…] indexed:0 read:2min 2026-09-10 ·